Problems and Countermeasures for Tunnel Construction by
Doubleshielded TBMs in Adverse Geological Conditions
Received date: 2007-02-25
Revised date: 2007-03-26
Online published: 2009-12-04
阐述了双护盾隧洞掘进机(TBM)在不良地质条件下施工所遇到的典型问题。并以昆明市掌鸠河引供水工程上公山隧洞TBM施工为例,对挤压及膨胀地层、断层破碎带、突泥、涌水等影响双护盾TBM的不良地质条件进行了分析研究,从宏观和微观角度提出了TBM通过不良地质情况的方案和措施,为今后双护盾硬岩掘进机施工借鉴、参考。
任国青 . 双护盾TBM不良地质施工问题及对策[J]. 隧道建设, 2007 , 27(3) : 108 -111 . DOI: A
Taking Shanggongshan tunnel on Zhangjiuhe River Water Diversion/Supply Project in Kunming, China as an example, the author analyzes such notorious adverse geological conditions as squeezing and/or swelling ground, fault and/or fracture zone, mud burst and water inflow that impede the boring of the doubleshielded TBMs and recommends options and countermeasures for these difficult geological conditions from the macro and micro viewpoints, which can provide reference for future tunnel construction by doubleshielded TBMs.
/
| 〈 |
|
〉 |