Analysis on Effects of Side Drifts in Construction of Largespan Tunnels
Received date: 2006-03-30
Online published: 2010-04-16
结合某大跨度城市交通隧道建设,通过二维弹塑性有限元数值模拟,对大跨度隧道施工中采用单侧壁导坑法时,导坑断面形状及大小对隧道地表沉降、拱顶沉降、仰拱隆起及支护受力的影响进行了研究,为隧道设计和施工提供了科学依据。
关键词: 大跨度隧道 侧壁导坑法 数值模拟
黄朱林 , 张志强 . 导坑在大跨度隧道施工中的影响分析[J]. 隧道建设, 2006 , 26(5) : 31 -33 . DOI: A
Taking the construction of a largespan urban traffic tunnel as example, for which single side drift method is adopted, the paper studies on the effects of different crosssection shapes and dimensions of side drifts on the ground surface subsidence, crown settlement, invert heaving and forces undertaken by the reinforcement structures by means of 2D elasticplastic finite element numerical simulations, which can provide basis for the design and construction of similar tunnels in the future.
/
| 〈 |
|
〉 |