Construction of Longfeng Tunnel Penetrating
across underneath Existing Jianshanzi Tunnel
Received date: 2006-01-16
Online published: 2010-04-16
比较全面地介绍了遂渝铁路引入线第2标段龙凤隧道下穿渝合高速公路尖山子隧道的施工方法。从施工总体原则与要求着手,依次介绍了主要施工步骤与方法:管棚施工、开挖及支护、施工监测、仰拱与衬砌施工等,同时简要介绍了应采取的相关防护措施、应急保证措施。
关键词: 隧道 下穿 施工方法
傅强 , 张细宝 . 龙凤隧道下穿尖山子隧道施工[J]. 隧道建设, 2006 , 26(5) : 66 -69 . DOI: B
The paper presents the construction method adopted for the construction of Longfeng tunnel on bid 2 section of approach line of SuiYu railway, which penetrates across underneath the existing Jianshanzi tunnel on Yuhe highway. From the general principles and requirements for the tunnel construction, the paper presents in detail such tunnel construction sequences as installation of piperoof protection, excavation and reinforcement, measurement and monitoring, installation of invert and lining. Furthermore, the paper briefly presents the protection measures and contingency countermeasures taken for the tunnel construction.
/
| 〈 |
|
〉 |