- CSCD核心中文核心科技核心
- RCCSE(A+)公路运输高质量期刊T1
- Ei CompendexScopusWJCI
- EBSCOPж(AJ)JST
收稿日期: 2006-06-26
修回日期: 2006-09-13
网络出版日期: 2009-12-11
Application of Partitioning Waterproofing in
Construction of Loushanguan Tunnel
Received date: 2006-06-26
Revised date: 2006-09-13
Online published: 2009-12-11
地下工程具有较严格的防水要求。传统的防水方式对地下工程渗漏病害没有彻底的解决办法。通过娄山关隧道施工中运用的分区防水,介绍分区防水的理念,及施工的工艺和过程。
韩光钦 . 分区防水在娄山关隧道施工中的应用[J]. 隧道建设, 2006 , 26(6) : 66 -68 . DOI: B
There are strict requirements for the waterproofing of underground works. By means of the traditional waterproofing technology, the water leakage defects of underground works can not be completely eliminated. Taking the partitioning waterproofing construction of Loushanguan tunnel as example, the author presents the concepts, construction technology and construction process of partitioning waterproofing of tunnels.
/
| 〈 |
|
〉 |