Construction Technology of Long Curved Hoisting Transportation System in Steep Inclined Shafts
Received date: 2009-07-03
Revised date: 2009-09-09
Online published: 2009-12-08
罗俊荣 . 大倾角斜井长曲线提升机运输施工技术[J]. 隧道建设, 2009 , 29(5) : 535 -542 . DOI: B
Fangdoushan tunnel in B12 contract section of ShiZhong expressway in Chongqing has smallradius, longcurve and steepgradient inclined ventilation shafts. If the existing sectionalized transportation method or conveyer belt transportation method is adopted for the inclined shafts, the safety level and transportation efficiency will be low. Owing to the installation of vertical pentagonal rollers in curved track sections and installation of steel rope clampers to the mining cars, the traction steel ropes are brought into restriction and the mining cars can travel along the curved tracks. Thereby, the track transportation system consisting of hoisting cranes, tracks and mining cars is applied in the smallradius longcurve inclined shafts. The transportation system has the characteristics of high safety, rapid construction speed and low cost. The development, design, testing, installation and operation of this technology are presented and the economical and social significances are analyzed.
/
| 〈 |
|
〉 |