Threebench Sixstep Rapid Construction Technology for
Large Span Tunnels in New Loess Ground
Received date: 2009-06-29
Revised date: 2009-09-14
Online published: 2010-01-04
以太中银铁路SJS-V标岗城隧道进口新黄土围岩洞身开挖为例,结合实际施工情况,以快速施工为目的就开挖方法作了论述。在新黄土地质条件下通过分部开挖减少围岩及初期支护变形量,省去临时支护,从而克服在该种围岩条件下因临时支护使工作面空间狭小的难题,通过方案优化,制定切实可行的对策,配套常规设备,实现快速施工。
祝扬军,杨佑权 . 新黄土大跨隧道三台阶六部开挖快速施工技术[J]. 隧道建设, 2009 , 29(增刊2) : 137 -143,210 . DOI: B
Taking the construction of the entrance section of Gangcheng tunnel of SJSV bid section on TaiyuanZhongweiYinchuan railway as an example, the authors discuss the rapid construction of tunnels in new loess ground in this paper. Sequential excavation is executed in new loess ground, which minimizes the deformation of the surrounding ground and the primary reinforcement and eliminates the need to install temporary support. In addition, sequential excavation method can solve the traditional problem of restricted working space induced by installing temporary support in new loess ground. The construction scheme is optimized, effective countermeasures are developed, ordinary equipments are allocated, which results in rapid construction of the tunnel in new loess ground.
/
| 〈 |
|
〉 |