- CSCD核心中文核心科技核心
- RCCSE(A+)公路运输高质量期刊T1
- Ei CompendexScopusWJCI
- EBSCOPж(AJ)JST
收稿日期: 2009-06-29
修回日期: 2008-09-07
网络出版日期: 2010-01-04
Application of Corekeeping Ring Cut Method in Yangtaishan Tunnel
Received date: 2009-06-29
Revised date: 2008-09-07
Online published: 2010-01-04
阐述环形开挖预留核心土法在羊台山隧道浅埋段开挖中的应用,重点介绍通过对环形开挖预留核心土法进行适当改进后的施工工艺,进一步说明改进后的工法优点及适用范围,供广大工程技术人员参考。
康铁军 . 环形开挖预留核心土法在羊台山隧道中的运用[J]. 隧道建设, 2009 , 29(增刊2) : 114 -116,176 . DOI: B
The application of corekeeping ring cut method in the excavation of the shallowburied section of Yangtaishan tunnel is presented, with the emphasis being placed on the presentation of the construction techniques of the optimized corekeeping ring cut method. The advantages and application scopes of the optimized corekeeping ring cut method is also presented. This paper can provide reference for tunneling colleagues.
/
| 〈 |
|
〉 |