Discussion on Rapid Curtain Grouting Technology in Xiangshan Tunnel
Received date: 2009-07-24
Revised date: 2010-01-08
Online published: 2010-05-11
易凯 , 张迎华 . 象山隧道帷幕注浆快速施工技术探讨[J]. 隧道建设, 2010 , 30(1) : 78 -83 . DOI: B
The curtain grouting constructions in 3 different hydrogeological sections of the main tunnel in No. 3 inclined shaft work lot of Xiangshan tunnel are compared. Three different grouting schemes, i.e., fullface curtain grouting, surrounding curtain grouting and local curtain grouting, are discussed. The influence of different grouting schemes on the construction efficiency under different hydrogeological conditions is analyzed. Optimal grouting schemes are determined, the grouting technology and the construction organization technology are optimized, which achieves better controlled construction cost and reduced construction period.
/
| 〈 |
|
〉 |