Study on Fullface Construction Scheme of
Fractured Section of Dabieshan Tunnel
Received date: 2006-06-30
Online published: 2010-04-21
周亚宇 . 大别山隧道围岩破碎带全断面开挖施工方案研究[J]. 隧道建设, 2006 , 26(4) : 54 -57 . DOI: A
Fullface construction is conducted for Dabieshan tunnel, which is a large crosssection tunnel on WuhanHefei passengerdedicated railway. TSP advance geology forecasting is conducted during the construction of the tunnel penetrating through the fractured surrounding rock mass, so as to determine the distance and strike of the fractured zone. On basis of the geological conditions exposed by the tunnel excavation, numerical simulation and theoretical analysis are performed by means of universal distinct element code (UDEC) for the tunnel excavation and reinforcement in the fractured zone. The measured results indicate that the crown settlement pattern obtained through calculations by means of UDEC coincides well with that obtained through insitu measurement and that the deformation values are lower than the designed allowable values, whichdemonstrates that thesurrounding rock mass and reinforcement structure of the tunnel are stable.
/
| 〈 |
|
〉 |