Rule of Timedependent Stress of Tunnels in Wet Subsidence
Loess Constructed by 3bench Excavation Method
Received date: 2010-01-04
Revised date: 2010-04-01
Online published: 2010-05-25
周烨 , 刘仲仁 , 刘兴平 , 胡锁滨 . 湿陷性黄土隧道三台阶法施工时间应变规律[J]. 隧道建设, 2010 , 30(2) : 128 -130,189 . DOI: A
The rule of the timedependent strains of the tunnels in wet subsidence loess ground is revealed by means of monitoring of the wet subsidence loess ground. A kind of 3bench construction method is developed on basis of the rule of the timedependent strains. The deformation behavior of the tunnels constructed by 3bench excavation method is summarized as follows: After top heading excavation, the tunnel stability can maintain 7 days before settlement occurs; During the excavation of the second bench, the controlled settlement of the primary reinforcement structure of the top heading is allowed, which is a stress releasing process; The settlement deformation caused by the third bench excavation is similar to that caused by the second bench excavation; When the ring is closed after invert installation, the ground tends to be stable. 3bench construction is executed under the guidance of the above deformation rule in the construction of LanzhouChongqing railway and satisfactory effects have been achieved.
Key words: wet subsidence loess; tunnel; 3 bench method; time dependent stress; rule
/
| 〈 |
|
〉 |