Comparative Analysis on Numerical Simulations of Threebench Excavation
Method and Twobench Excavation Method: Case Study on Zhifang Tunnel
Received date: 2010-01-11
Revised date: 2010-03-08
Online published: 2010-05-25
席俊杰 , 李德武 . 纸坊隧道三台阶与两台阶开挖数值模拟对比分析[J]. 隧道建设, 2010 , 30(2) : 147 -150 . DOI: B
Numerical simulation is made for the threebench sevenstep excavation method and twobench fivestep excavation method adopted in the construction of Zhifang tunnel located in carbonaceous slate ground. The deformation of the tunnel and the stresses acting on the primary reinforcement structure and the secondary lining under the condition of the above two excavation methods are analyzed. The analysis indicates that twobench fivestep excavation method is superior to threebench sevenstep excavation method in aspect of deformation control; however, under the condition of twobench fivestep excavation method, the axial forces of the steel ribs and the stresses on the primary shotcrete and the secondary lining at the arch lumbar and the side wall have increasing tendency, except the fact that the axial forces of the bolts reduce.
/
| 〈 |
|
〉 |