Construction Technology for Shallowburied
Tunnels in Grade VI Plasticflow Ground
Received date: 2010-01-04
Revised date: 2010-03-11
Online published: 2010-05-25
解方亮 . 软流塑状Ⅵ级围岩浅埋隧道施工技术[J]. 隧道建设, 2010 , 30(2) : 186 -189 . DOI: B
The exit portal section of Nanping tunnel on LanzhouChongqing railway is located in Grade VI plasticflow ground with unsymmetrical pressure. Pipe plies are installed from the ground surface to control the collapse of the plasticflow ground; enlarged arch feet and strengthened reinforcement are adopted to control deformation and collapse; 3bench excavation method with core soil is adopted on basis of construction scheme analysis and strict monitoring is performed inside and outside the tunnel. In the end, the tunnel driving successfully passes the shallowburied Grade VI ground with unsymmetrical pressure.
/
| 〈 |
|
〉 |