比较分析了用于隧道衬砌的全液压模板台车和简易衬砌台车的施工方法、设备配置、洞内布置、劳动力配置、工序循环时间等情况,最后对两者不同的使用条件提出了看法。
Abstract:
The article makes a comparison between the fullhydraulic steel formworks lining trolleys and simple steel formworks lining trolleys in such terms of construction methods, equipment allocations, inside tunnel arrangements, manpower organizations and cycle durations. The article also provides some suggestions on the different application conditions of the two types of lining trolleys.
Key words: fullhydraulic steel formworks lining trolley  , simple steel formworks lining trolley  , tunnel lining
贾文武. 隧道衬砌施工方案比较[J]. 隧道建设, 2005, 25(6): 42-43,46.
GU Wen-Wu. Comparison of Different Tunnel Lining Construction Schemes[J]. Tunnel Construction, 2005, 25(6): 42-43,46.