摘要:
北京地铁五号线崇文门车站从既有环线地铁之下穿过,车站拱顶上缘距既有线底板下缘只有1.98m,以大管棚作为超前支护。本文介绍了大管棚施工的主要技术措施和控制地层沉降的方法,分析管棚的变形机理,对实测变形值和计算值进行了比较。
Abstract:
Chongwenmen Metro station of No.5 line of Beijing Metro crosses underneath the existing Metro line, with the distance between the vault of Chongwenmen Metro station and the soleplate of the existing Metro line being only 1.98m. Piperoofs consisting of huge steel pipes are installed as advance reinforcement. The paper introduces the major technologic measures of the construction of the piperoofs and the ground settlement control methods, analyses the distortion mechanisms of the piperoofs and compares the measured distortion values with the calculated values.
Key words:  , piperoof construction distortion mechanism analysis
中图分类号:
 
U231+.3
陈浩, 姜景山, 姚海波. 崇文门车站过既有线管棚施工及变形分析[J]. 隧道建设, 2006, 26(1): 78-80.
CHEN Gao, JIANG Jing-Shan, TAO Hai-Bei. Construction and Distortion Analysis of Piperoof Installed in Chongwenmen Metro Station Underneath Existing Metro Line[J]. Tunnel Construction, 2006, 26(1): 78-80.