土岩组合地层盖挖法车站“吊脚桩”基坑设计优化研究

田海光   

  1. (中铁第一勘察设计院集团有限公司, 陕西西安 710043 )
  • 收稿日期:2015-03-06 修回日期:2015-04-27 出版日期:2015-07-20 发布日期:2015-07-29
  • 作者简介:田海光(1979—),男,河北石家庄人,2000年毕业于石家庄铁道学院,交通土建专业,本科,高级工程师,现从事地铁结构设计和技术管理工作。

Case Study on Design Optimization of Endsuspended Piles of Foundation Pit of a Cutandcover Metro Station in Soilrock Combined Strata

TIAN Haiguang   

  1. (China Railway First Survey and Design Institute Group Co., Ltd., Xi’an 710043, Shaanxi, China)
  • Received:2015-03-06 Revised:2015-04-27 Online:2015-07-20 Published:2015-07-29

摘要:

以青岛地铁3号线五四广场站为研究对象,对土岩组合地层地区的吊脚桩设计要点进行研究。通过数模模拟,对土岩组合地层中“吊脚桩”基坑的支护体系变形及内力、“吊脚桩”嵌岩深度与预留岩肩宽度的关系进行了分析,并对有竖向荷载的“吊脚桩”进行了研究。研究表明: 1)随着开挖深度的增加及锚杆的施工,预应力锁脚锚杆对吊脚桩桩底水平位移的控制作用明显。2)随着嵌岩深度和肩岩宽度的增加,吊脚桩桩身最大水平位移呈减小趋势,嵌岩深度取2.0 m,岩肩宽度取1.5 m较为合理。3)由于桩脚嵌入中风化花岗岩,桩顶位移不受竖向荷载控制,仅随开挖深度增加而明显增加;桩身弯矩稍有增大,但变化值极小。

关键词: 土岩组合地层, 盖挖法地铁车站, 吊脚桩, 嵌岩深度, 岩肩宽度

Abstract:

In the paper, the design of the endsuspended piles of the foundation pit of May Fourth Square Station of Line 3 of Qingdao Metro, which is located in soilrock combined strata, is studied. The correlation between the deformation and internal forces of the support system of the foundation pit with endsuspended piles located in soilrock combined strata and the rocksocketed depth and rock shoulder width of the endsuspended piles is analyzed by means of numerical simulation. Furthermore, the displacement and bending moment of the endsuspended piles with vertical load and without vertical load are also studied. Conclusions drawn are as follows: 1) With the increase of the cutting depth and the installation of the rock bolts, the prestressed footlocking rock bolts have obvious effect in the control of the horizontal displacement of the ends of the endsuspended piles; 2) With the increase of the rocksocketed depth and rock shoulder width, the maximum horizontal displacement of the endsuspended piles reduces; It is proper that the rocksocketed depth should be taken as 2.0 m and the rock shoulder width should be taken as 1.5 m; 3) Because the ends of the piles are socketed into the intermediatelyweathered granite, the displacement of the pile top is not controlled by the vertical load, however, it increases obviously as the cutting depth increases; the bending moment of the pile increases slightly, with very small increment. 

Key words: soilrock combined strata, cut and cover, Metro station, endsuspended pile, rocksocketed depth, rockshoulder width