摘要: : 玉磨铁路新平隧道位于断裂破碎带中,地质条件复杂,施工过程中突泥涌水灾害频发,其突发性及规模属国内外罕见。 为确 保隧道工程的顺利实施,在隧道设计、施工过程中,经过研究论证、方案比选优化、现场试验和重难点技术攻关,成功解决断裂破碎 带隧道施工技术难题,形成断裂破碎带含水体超前预报技术、隧道超前预加固技术、断裂带软岩大变形控制技术、带仰拱一次开挖 技术、隧道非爆开挖技术等一系列关键技术成果。
关键词: 玉磨铁路新平隧道, 断裂破碎带, 突泥涌水, 超前预报, 超前预加固, 大变形控制, 非爆开挖
Abstract: The Xinping Tunnel on Yuxi-Mohan Railway is located in the fault and fracture zone with complex geological conditions. During the construction process, mud and water gushing occur frequently, which are rare around the world. Hence, in order to ensure the successful implementation of the tunnel, key construction technologies for the tunnel crossing fault and fracture zone are obtained in terms of tunnel design and construction, research and discussion, scheme comparison and optimization, field experiment and difficulty treatment. The obtained technologies include advance prediction, advance pre-reinforcement, soft rock large deformation control, one-time excavation with invert, and nonexplosive excavation.
Key words: Xinping Tunnel on Yuxi-Mohan Railway, fault and fracture zone, mud and water gushing, advance prediction, advance pre-reinforcement, large deformation control, non-explosive tunneling
中图分类号:
U 45
赵前进, 李敬伟. 玉磨铁路新平隧道穿越密集断裂带施工关键技术[J]. 隧道建设, 2019, 39(12): 2058-.
ZHAO Qianjin, LI Jingwei. Key Construction Technology for Xinping Tunnel on Yuxi-Mohan Railway Crossing Dense Fault and Fracture Zone [J]. Tunnel Construction, 2019, 39(12): 2058-.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://www.suidaojs.com/CN/10.3973/j.issn.2096-4498.2019.12.017
http://www.suidaojs.com/CN/Y2019/V39/I12/2058
土砂互层隧道大变形控制技术研究——以浩吉铁路阳城隧道为例
高黎贡山隧道敞开式TBM穿越高压富水软弱破碎 蚀变构造带施工技术