隧道建设(中英文) ›› 2025, Vol. 45 ›› Issue (S1): 351-360.DOI: 10.3973/j.issn.2096-4498.2025.S1.034

• 施工机械 • 上一篇    

适用于超长距离的硬岩顶管机关键技术研究及应用

王盟盟, 范磊, 孙英杰, 陈家浩   

  1. (中铁工程装备集团有限公司, 河南 郑州 450016
  • 出版日期:2025-07-15 发布日期:2025-07-15
  • 作者简介:王盟盟(1993—),男,陕西商洛人,2018年毕业于兰州交通大学,土木工程专业,本科,工程师,主要从事隧道掘进机设计与制造的项目管理工作。E-mail: 271034145@qq.com。

Key Technologies of Pipe Jacking Machines for Extra-Long Distance Hard Rocks and Their Application

WANG Mengmeng, FAN Lei, SUN Yingjie, CHEN Jiahao   

  1. (China Railway Engineering Equipment Group Co., Ltd., Zhengzhou 450016, Henan, China)
  • Online:2025-07-15 Published:2025-07-15

摘要: 为解决硬岩顶管机在超长距离隧洞施工中面临的触变泥浆异常流失、集渣、返渣以及主顶顶推力分散造成顶推力不足等难题,依托河南省汝阳县前坪供水3#隧洞施工项目,设计、研发机械化非开挖设备硬岩顶管机,对协同联动助推系统、封浆挡渣减阻系统、泥水环流系统和收渣系统等关键技术进行研究;通过分析试验数据,构建实际顶推力模型。结果显示: 1)该设备在不超过最大负荷16 000 kN条件下,能够满足单轴抗压强度Rc195.93 MPa的破岩能力; 2)1 535 m隧道施工过程中,仅开启协同联动装置和23号中继间,即可满足隧道顶进施工所需的顶推力。

关键词: 超长距离隧洞, 硬岩顶管机, 协同联动助推装置, 封浆装置, 收渣系统, 泥水环流系统

Abstract: When a hard rock pipe jacking machine bored in an extra-long tunnel, phenomena of abnormal loss of thixotropic slurry, accumulation of debris, backflow of debris, and main thrust force dispersion-caused insufficient jacking force occurred. A case study is conducted on the #3 tunnel of Qianping water supply project in Ruyang, China, and a mechanized trenchless equipment, a hard rock pipe jacking machine, is designed and developed. Key technologies of coordinated linkage booster system, slurry-sealing device, debris collection system, and mud-water circulation system are analyzed. By analyzing the test data, a real jacking force model is established. The results show that: (1) Under a maximum load of no more than 16 000 kN, the rock-breaking capacity of the equipment meets the requirement of uniaxial compressive strength Rc> 195.93 MPa. (2) The coordinated linkage device and the #2 and #3 relay chambers of the equipment are activated in a 1 535 m-long tunnel, reaching required jacking force for tunnel jacking construction.

Key words: extra-long distance tunnel, hard rock pipe jacking machine, synergistic linkage booster, slurry-sealing device, debris collection system, mud-water circulation system