基于“4M1E”影响因素的敞开式TBM快速掘进保障措施
收稿日期: 2013-07-29
修回日期: 2013-11-20
网络出版日期: 2014-06-16
Measures to Ensure Rapid Boring of Open TBM Based on “4M+1E” Factors
Received date: 2013-07-29
Revised date: 2013-11-20
Online published: 2014-06-16
徐赞 , 谢培才 . 基于“4M1E”影响因素的敞开式TBM快速掘进保障措施[J]. 隧道建设, 2014 , 34(6) : 569 -575 . DOI: 10.3973/j.issn.1672-741X.2014.06.012
Tunneling by TBM is a complex and systematic project, which involves many disciplinary fields and has multiple constraints. Ensuring the availability of the equipment and accelerating the construction progress are keys of tunneling by TBM. Factors affecting TBM tunneling can be summarized as “4M+1E” (Man, Machine, Material, Method and Environment). The study result shows that highquality management team, good equipment condition and scientific management of material supply, construction methods and environment can bring man’s initiatives into full play, can minimize the construction risks, can make full use of the advantages of the equipment and can achieve rapid boring.
/
| 〈 |
|
〉 |