Study on Construction Scheme of Xinzhou Tunnel Crossing Underneath DatongYuncheng Highway
Received date: 2014-09-08
Revised date: 2014-09-14
Online published: 2014-11-20
王洪昌 , 马志富 , 曾青 , 奂光坤 . 忻州隧道下穿大运高速公路技术方案研究[J]. 隧道建设, 2014 , 34(11) : 1082 -1086 . DOI: 10.3973/j.issn.1672-741X.2014.11.011
Xinzhou tunnel on DatongXi’an passengerdedicated railway crosses underneath DatongYuncheng highway. Therefore, serious ground surface settlement and safety risks may occur in the construction of Xinzhou tunnel. In the paper, 3D simulation is made on the construction of the section of Xinzhou tunnel crossing underneath DatongYuncheng highway by means of ADECRRS and NATM, and study is made on the feasibility of different design parameters and different construction schemes, as well as on the influence on the ground surface settlement. Conclusion is drawn that the construction of the section of Xinzhou tunnel crossing underneath DatongYuncheng highway by means of ADECRRS and NATM is feasible, with the design parameters as follows: excavation by double side heading method, cyclic advance rate being 8 m, reinforcing of the top heading with 4 m reinforcement overlap, advance support by 120 m pipe roof, short advance rate and early ring closing.
Key words: ADECORS; tunneling under shallow cover; loess; highway tunnel; numerical simulation
/
| 〈 |
|
〉 |