突变载荷下盾构刀盘设计验证分析
收稿日期: 2015-04-08
修回日期: 2015-07-29
网络出版日期: 2015-09-22
基金资助
国家重点基础研究发展计划(973)资助项目(2014CB046906); 郑州市重大科技专项(141PZDZX005)
Verification Analysis on Design of Shield Cutterhead under Abruptchanging Loading Conditions
Received date: 2015-04-08
Revised date: 2015-07-29
Online published: 2015-09-22
韩伟锋 , 陈馈 , 张兵 . 突变载荷下盾构刀盘设计验证分析[J]. 隧道建设, 2015 , 35(9) : 957 -961 . DOI: 10.3973/j.issn.1672-741X.2015.09.016
Due to the unstable loading conditions in complex geological environment, shield boring may face such problems as uneven pressure on the cutterhead, vibration and deformation of cutterhead and abnormal damage of cutting tools. In the paper, the stress and strain conditions of the cutterhead under unstable loading conditions are analyzed by means of finite element method and on basis of the actual parameters of the cutterhead and strata in the site. In the end, the stressstrain conditions of the cutterhead of the shield under the unstable loading conditions in the mentioned strata are obtained and the reliability of the cutterhead design is ensured.
Key words: shield; cutter head; abruptchanging loading; finite element analysis; stressstrain
/
| 〈 |
|
〉 |