西安地铁穿越湿陷性黄土层处理原则与措施研究
收稿日期: 2015-08-03
修回日期: 2015-10-08
网络出版日期: 2016-03-30
Treating Principle of and Countermeasures for Collapsible Loess: Case Study on Lintong Line of Xi’an Metro
Received date: 2015-08-03
Revised date: 2015-10-08
Online published: 2016-03-30
罗章波 . 西安地铁穿越湿陷性黄土层处理原则与措施研究[J]. 隧道建设, 2016 , 36(3) : 257 -263 . DOI: 10.3973/j.issn.1672-741X.2016.03.002
Part of the Metro stations and tunnel sections on Lintong Line of Xi’an Metro cross dead weight collapsible loess. In this paper, the stressing conditions and probability of environmental change of foundation of Metro projects are analyzed and studied. And then the treating principle of and countermeasures for collapsible loess are proposed. The collapsible probability of Lintong Line of Xi’an Metro is estimated; the collapsible deformation of the loess and structural stress are calculated; the stress deformation and stressstrain characteristics of the structure at different connection points of Metro projects are analyzed. Finally, some countermeasures for collapsible loess of Metro tunnel, mined tunnel and shield tunnel are proposed. The resalts can provide reference for the design and construction of Xi’an Metro and other similar projects.
Key words: Metro station; collapsible loess layer; foundation; mined tunnel; shield tunnel
/
| 〈 |
|
〉 |