(1. 中国矿业大学(北京)力学与建筑工程学院,北京 100083; 2. 北京市轨道交通建设管理有限公司, 北京 100068;3. 城市轨道交通全自动运行系统与安全监控北京市重点实验室, 北京 100068;4. 中铁十四局集团有限公司, 山东 济南 250014; 5. 北京城建集团有限责任公司博士后科研工作站, 北京 100088)
网络出版日期: 2022-09-09
Application of LongDistance Construction and Transportation Model of Earth [JP3]Pressure Balance Shield Used in Phase 1 Project of Beijing Metro New Airport Line
(1.School of Mechanics and Civil Engineering,China University of Mining and Technology Beijing,Beijing 100083,China;2.Beijing MTR Construction Administration Corporation,Beijing 100068,China;3.Key Laboratory of Fully Automatic Operation and Safety Monitoring for Urban Rail Transit, Beijing 100068,China;4.China Railway 14th Bureau Group Corporation Limited,Jinan 250014,Shandong,China;5.Postdoctoral Program Beijing Urban Construction Group Co.,Ltd.,Beijing 100088,China)
Online published: 2022-09-09
杨志勇
,
白志强
,
李元凯
,
高洪吉
,
江玉生
,
孙伟
,
孙正阳
.
土压平衡盾构长距离施工运输模型应用研究——以北京地铁新机场线一期工程为例
In order to improve the construction efficiency of the earth pressure balance(EPB) shield tunnel transportation system, a case study is conducted on the phase 1 project of Beijing metro new airport line. Furthermore, two adjacent shield sections with different muck transportation modes are selected to establish a construction material and muck transportation model of the EPB shield. In addition, two transport modes, the rail transport system and rail transport + belt conveyor (including horizontal continuous belt conveyor + vertical belt conveyor) combined system, are compared and analyzed. The results reveal the following: (1) The rail transport system is preferred when the transport distance is less than 600 m. (2) When the transportation distance is between 600 m and 1 700 m, the construction efficiency of the two methods is essentially identical. (3) When the transportation distance is greater than 1 700 m, the combined transportation system should be preferred. Compared with the combined transportation system, the onsite construction continuity of the rail transportation system is poor, the measured tunneling cycle time is larger than the theoretical prediction, and the time difference increases gradually with the transportation distance. Compared with the theoretical prediction, the measured driving cycle time difference of the combined transportation system is smaller, and it is easier to reach the ideal construction expectation in the actual construction process.
/
| 〈 |
|
〉 |