Numerical Analysis of Seepage Characteristics and Stability of Cofferdam in East Artificial Island of ShenzhenZhongshan Link During Pumping
(1.China Railway Tunnel Consultants Co.,Ltd.,Guangzhou 511458,Guangdong,China;2.Key Laboratory of Intelligent Monitoring and Maintenance of Tunnel Structure,CRTG,Guangzhou 511458,Guangdong,China;3.Central South University, Changsha 410000,Hunan,China)
Online published: 2023-03-24
许俊伟 , 汪华坡 . 深中通道东人工岛围堰抽水过程渗流特性及稳定性分析[J]. 隧道建设, 2022 , 42(S2) : 168 -174 . DOI: 10.3973/j.issn.2096-4498.2022.S2.020
To investigate the influence of the internal pumping process on the seepage field and stability of the cofferdam body after the closure of the artificial island cofferdam, a case study is conducted on the island cofferdam project of the largescale marine traffic hub on the east artificial island of the ShenzhenZhongshan link. Then, the finite element analysis software Geostudio is applied to establish the internal precipitation construction model of the cofferdam under different pumping conditions, and the stability analysis of cofferdam seepage field and slope is carried out during the pumping process to provide reference for the actual construction. The results show that: (1) The cofferdam body tends to be more unstable when the seepage concentrated at the foot of the slope on the backwater side at a higher pumping speed with higher wetting line. (2) The deformation of the cofferdam mainly occurs in softbase silt layer with slight displacement of the cofferdam itself, and the pumping speed has little effect on the displacement of the cofferdam, which indicates that additional reinforcement measures, such as replacement and highpressure jet grouting, are needed for the seabed foundation silt layer at the early stage of cofferdam filling. Furthermore, the analysis of the cofferdam slope stability with the limit equilibrium show that the safety factor of the cofferdam slope first decreases and then increases with the decreasing inner water level. In addition, a smaller minimum safety factor is obtained for a higher pumping speed. Considering the limitation of site construction progress, it is recommended to select the pumping speed of 1 m/d on the premise of meeting the stability of weir slope.
/
| 〈 |
|
〉 |