隧道建设(中英文) ›› 2016, Vol. 36 ›› Issue (9): 1106-1113.DOI: 10.3973/j.issn.1672-741X.2016.09.012
• 施工技术 • 上一篇 下一篇
谢震灵, 何晓波
收稿日期:
修回日期:
出版日期:
发布日期:
作者简介:
XIE Zhenling, HE Xiaobo
Received:
Revised:
Online:
Published:
摘要:
针对红谷隧道一期管节沉放安装施工中产生的轴线偏差问题,介绍管节沉放安装工艺,总结管节沉放安装轴线偏差的影响因素和常用的纠偏方法,分析红谷隧道一期管节沉放安装施工产生轴线偏差的原因,采用横向错位法和摆尾法对一期沉放出现的轴线偏差进行纠偏,一期管节最终的轴线偏差控制在设计允许范围内。从钢端壳制作精度、横向水流和沉放测量精度等方面对二期管节沉放轴线控制提出建议,以期为今后的沉管隧道管节沉放施工提供借鉴。
关键词: 沉管隧道, 管节沉放, 管节纠偏, 横向错位法, 摆尾法
Abstract:
The sinking and installation technologies for Honggu Tunnel in Nanchang are introduced. The influencing factors of deviation of tunnel segment and deviation rectification methods are summarized. The horizontal dislocation method and segment tail swing method are adopted for deviation rectification of tunnel segment of Phase 1 of Honggu Tunnel. The construction effect is good. Suggestions are given for axial line control of tunnel segment sinking of Phase 2 of Honggu Tunnel in terms of steel end shell manufacturing accuracy, horizontal flow velocity and segment sinking monitoring accuracy.
Key words: immersed tunnel, tunnel segment sinking, tunnel segment deviation rectification, horizontal dislocation method, tail swing method
中图分类号:
U 455
谢震灵, 何晓波. 南昌红谷隧道管节安装纠偏施工技术[J]. 隧道建设, 2016, 36(9): 1106-1113.
XIE Zhenling, HE Xiaobo. Deviation Rectification Technologies for Segment Installation of Honggu Tunnel in Nanchang[J]. Tunnel Construction, 2016, 36(9): 1106-1113.