Fully Prefabricated Assembling Technology of Tsinghuayuan  Tunnel in BeijingZhangjiakou Highspeed Railway(京张高铁清华园隧道轨下结构预制拼装技术)

LYU Gang1, LIU Jianyou1, *, ZHAO Yong2, LIU Fang1, WANG Zhiwei3   

  1. (1. China Railway Engineering Consulting Group Co., Ltd., Beijing 100055, China;  2. China Railway Economic and Planing Research Institute, Beijing 100844, China;  3. China Academy of Railway Sciences Corporation Limited, Beijing 100081, China)
  • 收稿日期:2019-02-27 修回日期:2019-05-13 出版日期:2019-08-20 发布日期:2019-09-04
  • 作者简介:吕刚(1976—),男,江苏句容人,2004年毕业于北京交通大学,桥梁与隧道工程专业,硕士,高级工程师,现从事隧道工程的设计和研究工作。Email: tzydglg@126.com。*通信作者: 刘建友, Email: 13522182378@163.com。

京张高铁清华园隧道轨下结构预制拼装技术

吕刚1, 刘建友1,*, 赵勇2, 刘方1, 王志伟3   

  1. (1. 中铁工程设计咨询集团有限公司, 北京 100055; 2. 中国铁路经济规划研究院, 北京 100844;  3. 中国铁道科学研究院集团有限公司, 北京 100081)
  • Received:2019-02-27 Revised:2019-05-13 Online:2019-08-20 Published:2019-09-04

摘要:

Tsinghuayuan Tunnel of BeijingZhangjiakou Highspeed Railway is the first fully prefabricated highspeed railway tunnel in China. The supporting structure, subrail structure, and subsidiary structure of Tsinghuayuan Tunnel are all prefabricated in the factory. The strength, deformation and stability of subrail structure are analyzed by numerical simulation method; a kind of threeblock type of subrail prefabricated structure is put forward according to prefabricated assembling technology; and the subrail space is used to ventilate and rescue under the stability condition. The connection between subrail structure and shield segment is the key to fullyprefabricated assembling technology. By introducing the grouting technology and construction keys of subrail structure, the stress on subrail structure and shield segment can be balanced. The results can provide reference for similar projects in the future.

关键词: highspeed railway tunnel, prefabricated assembling technology, shield tunnel, subrail structure, grouting

Abstract:

京张高铁清华园隧道是国内第一座全预制拼装的高铁隧道,其支护结构、轨下结构和附属结构均采用工厂化预制,并研发了拼装机器人,实现了隧道全预制拼装施工。采用数值模拟方法,分析轨下结构的强度、变形和稳定性,并根据预制拼装施工工艺的要求,提出一种3块式轨下预制结构,在满足稳定性要求的前提下,利用轨下空间为隧道提供通风和救援通道。轨下结构与盾构管片的连接是全预制拼装结构的关键技术,通过阐述轨下结构的注浆工艺及其施工要点,确保轨下结构与盾构管片受力均匀,可为今后类似工程的建设提供借鉴。

Key words: 高铁隧道, 全预制拼装技术, 盾构隧道, 轨下结构, 注浆