隧道建设(中英文) ›› 2020, Vol. 40 ›› Issue (10): 1433-1440.DOI: 10.3973/j.issn.2096-4498.2020.10.006

• 研究与探索 • 上一篇    下一篇

襄阳东西轴线项目沉管预制局部块体试验研究

王聪1 2 3, 彭浩4   

  1. 1.中交第二航务工程局有限公司,湖北 武汉 430040;2.长大桥梁建设施工技术交通行业重点实验室,湖北 武汉 430040;3.交通运输行业交通基础设施智能制造技术研发中心,湖北 武汉 430040;4.中交第二航务工程局有限公司第五工程分公司,湖北 武汉 430040)

  • 出版日期:2020-10-20 发布日期:2020-11-01
  • 作者简介:王聪(1987—),男,山东日照人,2014年毕业于大连理工大学,港口、海岸及近海工程专业,硕士,工程师,主要从事水运工程工作。E-mail: 798938976@qq.com。

Experimental Study on Prefabricated Partial Block of Immersed Tunnel of Xiangyang East-West Axis Project

WANG Cong1, 2, 3, PENG Hao4   

  1. (1.CCCC Second Harbor Engineering Co., Ltd.,Wuhan 430040,Hubei,China;2.Key Laboratory of Large-span Bridge Construction Technology, Wuhan 430040,Hubei,China;3.Research and Development Center of Transport  Industry of Intelligent Manufacturing Technologies of Transport Infrastructure, Wuhan 430040,Hubei,China;4.Fifth Engineering Branch of CCCC Second Harbor Engineering Co., Ltd.,Wuhan 430040,Hubei,China)

  • Online:2020-10-20 Published:2020-11-01

摘要: 襄阳市东西轴线项目沉管预制采用节段整体式全断面顺浇法,具有高强度、大断面、大体积的特点,管节控裂难度较大。为验证混凝土配合比、施工工艺以及裂缝控制措施的可行性及可靠性,采用Midas FEA软件,进行沉管管节在设计工况下的水化热温度应力数值仿真模拟计算,分析管节浇筑过程中混凝土内部温度及应力变化情况。数值仿真结果表明,管节连接处抗裂安全系数较低。进而选取理论开裂风险最高的边墙倒角位置和施工难度最高的中隔墙倒角位置进行模型试验,实际模拟钢筋及预埋件施工工序,全面检验原材料、配合比和混凝土施工性能的可靠性,并布设智能温度监测系统。通过局部块体试验,合理优化钢筋及预埋件的结构形式和安装工序,验证混凝土性能并优选施工配合比;同时,通过提出的原材料温控标准对模型试验进行温度智能监测数据分析。

关键词: 沉管隧道, 沉管预制, 数值仿真, 局部块体试验, 安装工序, 施工配合比, 温控措施

Abstract: The immersed tunnel segments of EastWest Axis Project in Xiangyang are prefabricated by integral fullsection down pouring method, which is characterized by high strength, large crosssection and large volume, and the segment crack is difficult to control. In order to verify the feasibility and reliability of concrete mixing proportion, construction technology and crack control measures, the finite element software Midas FEA is used to conduct numerical simulation and calculation on hydration heat temperature stress of immersed tunnel joints under design conditions, and the internal temperature and stress variation of concrete during the casting of immersed tunnel segment are analyzed. The numerical simulation results show that the anticracking safety factor at the joint is low. Therefore, the chamfering position of the sidewall with the highest theoretical cracking risk and that of the middle separation wall with the highest construction difficulty are selected for model test. In the model test, the construction process of reinforced bars and embedded parts is simulated, the reliability of raw materials, mixing proportion, concrete construction performance, etc. are comprehensively checked, and an intelligent temperature monitoring system is set up. Through the partial block test, the structural types and installation procedures of reinforced bars and embedded parts are rationally optimized, so as to validate the concrete performance and optimize the construction mixing proportion. Meanwhile, the raw material temperature control standards are proposed to analyze the monitoring data for model testing.

Key words: immersed tunnel, immersed tunnel segment prefabrication, numerical simulation, partial block experiment, installation procedures, construction mixing proportion, temperature control measures