摘要:
为了解决隧道衬砌变形和裂缝病害问题,首先对茜阳隧道病害状况和原因进行分析,提出隧道病害整治方案:换拱方案和明挖方案。然后,通过对塑性区、初期支护内力和安全系数进行数值模拟分析,得出换拱并注浆改善围岩条件是最为有效的方法。最后,提出了综合处理隧道裂缝的具体措施,方案实施后,地表沉降、拱顶下沉、洞周收敛趋于稳定。
关键词: 茜阳隧道, 隧道病害, 数值模拟, 换拱方案, 明挖方案
Abstract:
Deformation and cracks occur to the lining of Xiyang tunnel. Analysis is made on the defect situation and the causes for the defects, and alternative solutions, i.e., arch replacing solution and cutandcover solution, are proposed. Numerical simulation analysis is made in terms of the plasticized zones, the internal forces of the primary support and the safety coefficient, which concludes that the arch replacing solution plus grouting to consolidate the surrounding rocks is the most effective solution. At last, countermeasures to cope with the cracks are proposed. After the solution is adopted, the ground surface settlement, crown settlement and convergence tend to be stable.
Key words: Xiyang tunnel, defect, numerical simulation, arch replacing, cut and cover method
吴启勇. 茜阳隧道出口病害处治技术研究[J]. 隧道建设, 2011, 31(3): 396-404.
TUN Qi-Yong. Study on Countermeasures for Defects of Exit Section of Xiyang Tunnel[J]. Tunnel Construction, 2011, 31(3): 396-404.