隧道建设(中英文) ›› 2022, Vol. 42 ›› Issue (S2): 345-351.DOI: 10.3973/j.issn.2096-4498.2022.S2.043

• 规划与设计 • 上一篇    下一篇

考虑地层影响的市政桥梁与地铁车站合建方案研究——以重庆大学城南站合建工程为例

黄翰霄1, 韦良文1, 2, *, 鄢玉鑫1   

  1. 1. 重庆交通大学土木工程学院, 重庆 400074 2. 重庆交通大学 省部共建山区桥梁及 隧道工程国家重点实验室, 重庆 400074

  • 出版日期:2022-12-30 发布日期:2023-03-24
  • 作者简介:黄翰霄(1997—),男,四川自贡人,重庆交通大学交通运输专业在读硕士,研究方向为隧道及地下工程。 Email: 834172822@qq.com。*通信作者: 韦良文, Email: weiliangwen@163.com。

Integrated Construction Scheme of Municipal Bridges and Metro Stations Considering Geological Condition: a Case of University City South Station in Chongqing

HUANG Hanxiao1, WEI Liangwen1, 2, *, YAN Yuxin1   

  1. (1. School of Civil Engineering, Chongqing Jiaotong Uniersity, Chongqing 400074, China; 2. State Key Laboratory of Mountain Bridge and Tunnel Engineering, Chongqing Jiaotong University, Chongqing 400074, China)

  • Online:2022-12-30 Published:2023-03-24

摘要: 市政桥梁与地铁车站合建时,为满足2种不同构筑物的结构安全和正常使用需求,保证结构合理受力,对比“低转换梁连接”及“桥墩与车站顶板固结结合部分换填”2种方案,建立三维地层-结构模型并进行计算,对各结构承载能力、变形情况及抗震能力进行分析。研究结果表明,采用“低转换梁连接方案”进行合建存在设计、施工困难,且运营期转换结构有检测、维护需求;采用“桥墩与车站顶板固结结合部分换填方案”进行合建可有效避免此类问题,且车站板、墙、柱等结构受力情况较“低转换梁方案”得到改善,同时方案对车站及桥墩能起到更好的变形控制效果,各结构承载力强度及变形均满足规范要求。

关键词: 地铁车站, 市政桥梁, 合建, 地层-结构模型, 受力分析, 变形控制, 抗震分析

Abstract: When municipal bridge and metro station are jointly built, the structural safety and normal use of the two different structures must be considered, and the structure can also be reasonably stressed. Two schemes of "connection of low transfer beams" and "bridge pier and station roof consolidation and partial replacement" are compared, and the bearing capacity, deformation and seismic capacity of each structure are analyzed through a threedimensional stratumstructure model. The research results show that it is difficult to design and construct the integrated structure with "low transfer beam connection scheme", and the transfer structure needs to be inspected and maintained during operation period; the integrated structure can be carried out using "bridge pier and station roof consolidation and partial replacement scheme". Such problems are effectively avoided, and the stress of the station slab, wall, column, and other structures is improved compared with the "low transfer beam scheme". The bearing capacity and deformation of each structure meet the requirements.

Key words: metro station, municipal bridge, integrated construction, stratastructure model, stress analysis, deformation control, seismic analysis