为解决盾构出洞接收时洞门漏水、漏浆影响盾构正常出洞的问题,以天津地铁6号线西青道站—南运河站区间盾构出洞施工中洞门漏水为例,通过采取明洞填充、隧道内注浆、盾壳开孔对洞门主体结构注聚氨酯、洞门冻结等应急措施确保了盾构顺利出洞。工程实践证明,以上方法对封堵泄漏水路溶腔等十分有效。
关键词: 土压平衡盾构, 盾构接收, 接收井漏水, 堵漏
Abstract:
The stopping of water leakage and slurry leakage of shield receiving shaft are very important and difficult. A series of technologies, i.e. filling of opencut tunnel, grouting in tunnel, polyurethane filling for main tunnel structure and tunnel portal freezing, have been adopted in water leakage stopping of shield receiving shaft of Xiqingdao StationNanyunhe Station section on Line No. 6 of Tianjin Metro. The construction results show that the abovementioned technologies are feasible and effective.
Key words: earth pressure balance shield, shield receiving, water leakage of shield receiving shaft, water leakage stopping
中图分类号:
U 455
李海, 朱长松. 天津地铁6号线西青道站—南运河站区间盾构到达接收措施失效处理实例[J]. 隧道建设, 2016, 36(12): 1512-1516.
LI Hai, ZHU Changsong. Countermeasures for Failure of Shield Receiving of Xiqingdao StationNanyunhe Station Section on Line No. 6 of Tianjin Metro[J]. Tunnel Construction, 2016, 36(12): 1512-1516.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://www.suidaojs.com/CN/10.3973/j.issn.1672-741X.2016.12.016
http://www.suidaojs.com/CN/Y2016/V36/I12/1512