南水北调中线一期穿黄隧洞工程地质条件复杂、施工难度巨大。对穿黄隧洞工程概况做了简要介绍,对隧洞施工方案、盾构设备选择、盾构施工应具备的进/出口条件、盾构施工步骤及辅助设施设置等进行了初步的探讨。
Abstract:
The geological conditions are complicated in the firststage construction of tunnels crossing Yellow River on the middle line of southtonorth water diversion project, which leads to having huge difficulties. The construction schemes, the style selection, the input and output conditions, the construction procedures and the auxiliary equipment in the construction of tunnels using the shield machine are discussed in this paper.
Key words: tunnel crossing Yellow River  , shield  , construction
中图分类号:
 
U455.43
杨恩文, 汪雪英. 盾构法施工在中线一期穿黄隧洞中的应用[J]. 隧道建设, 2007, 27(增刊): 378-381.
YANG En-Wen, HONG Xue-Yang. Application of Shield Machine in Construction of tunnels Crossing Yellow River on Middle Line of SouthtoNorth Water Diversion Project[J]. Tunnel Construction, 2007, 27(增刊): 378-381.
0 / / 推荐
导出引用管理器 EndNote|Ris|BibTeX
链接本文: http://www.suidaojs.com/CN/B
http://www.suidaojs.com/CN/Y2007/V27/I增刊/378