隧道建设(中英文) ›› 2010, Vol. 30 ›› Issue (S1): 410-414.

• 施工技术 • 上一篇    下一篇

超前地质预报在连云港后云台山隧道围岩分级中的应用

程晋源1,蔺宁君2,李晓昭1,程知言1,王益壮1,袁亮1,徐振红2   

  1. 1. 南京大学华东有色地勘局地下空间与地质环境研究所,南京221007;
    2. 连云港市疏港道路建设办公室,江苏连云港222006
  • 收稿日期:2010-04-19 修回日期:2010-06-08 出版日期:2010-08-14 发布日期:2010-08-25
  • 作者简介:程晋源(1982—),男,山西太原人,毕业于中国矿业大学岩土工程专业,硕士,工程师,主要从事岩土力学、矿山和隧道工程等领域的技术开发和科研工作。
  • 基金资助:

    国防科工委“十一五”项目(科工计[2007]825号)

Application of Advance Geology Forecast in Surrounding
Rock Mass Classification:  Case Study on Houyuntaishan Tunnel

 CHENG  Jin-Yuan1, LIN  Ning-Jun2, LI  Xiao-Zhao1, CHENG  Zhi-Yan1, WANG  Yi-Zhuang1, YUAN  Liang1, XU  Zhen-Gong2   

  1. 1. NJUECE Institute for Underground Space and Geoenvironment, Nanjing 221007;
    2. Lianyungang Headquarters of Expressway Construction, Lianyungang 222206, Jiangsu
  • Received:2010-04-19 Revised:2010-06-08 Online:2010-08-14 Published:2010-08-25

摘要:

针对连云港后云台山隧道可能会出现的各种地质灾害,为了在施工前期探明掌子面前方的复杂地质情况并进行稳定性预测分析,提出应坚持从工程实际出发、合理选择、综合使用有效的方法和手段,制定背景项目的超前地质预报工作方案。其能充分发挥各种方法和手段的特长,对隧道围岩等级进行预测评定,为隧道围岩的稳定和施工安全提供有力保证。并经实践证明,采用综合超前地质预报方法预测围岩等级,总体预报准确率达到80%以上。

关键词: 隧道, 围岩等级, TSP, 地质雷达, 超前地质预报

Abstract:

The geological hazards that may occur during the construction of Houyuntaishan tunnel in Lianyungang are addressed in the paper. Proper and efficient advance geology forecast methods are adopted on basis of the actual engineering conditions so as to predict the complex geological conditions and analyze the stability of the surrounding rock mass in advance. Proper advance geology forecast execution plan is established for the tunnel, which can give full play to the adopted advance geology forecast methods, predict and evaluate the grades of the surrounding rock mass and provide strong guarantees for the stability of the surrounding rock mass and for the safety of the tunnel construction. The practice demonstrates that the comprehensive advance geology forecast methods adopted have achieved 80% accuracy.

Key words: tunnel, surrounding rock mass classification, TSP, GPR, advance geology forecast