四线大断面隧道浅埋暗挖下穿综合管廊保护方案研究——以广佛城际下穿华康道管廊工程为例

吉艳雷1, 2   

  1. 1. 中铁第一勘察设计院集团有限公司, 陕西 西安 710043;2. 陕西省铁道及地下交通工程重点实验室(中铁一院), 陕西 西安 710043)

  • 出版日期:2021-07-20 发布日期:2021-07-29
  • 作者简介:吉艳雷(1982—),男,山西运城人,2008年毕业于西南交通大学,隧道工程专业,硕士,高级工程师,主要从事地下工程设计研究工作。E-mail:365941113@qq.com。
  • 基金资助:
    中铁第一勘察设计院集团有限公司科研项目(院科12-07,院科20-01

Protection Scheme for Shallow Buried Fourth Track Tunnel with Large Cross Section Passing beneath a Utility Tunnel: a Case Study on GuangzhouFoshan Intercity Passing beneath Huakang Road Utility Tunnel

JI Yanlei1 2   

  1. (1. China Railway First Survey and Design Institute Group Co., Ltd.Xi′an 710043, Shaanxi, China; 2.Shaanxi Railway and Underground Traffic Engineering Key Laboratory (FSDI), Xi′an 710043, Shaanxi, China)

  • Online:2021-07-20 Published:2021-07-29

摘要: 为解决软弱富水地层四线大断面隧道近距离下穿大型综合管廊的支护及沉降控制技术难题,以广佛城际下穿华康道管廊工程为例,通过案例调研、方案比选、数值模拟分析及现场监测的方法,对超前加固方案、暗挖支护参数、施工工法、施工工艺等开展研究。研究结果表明: 1)管廊底部设置托底管棚+隧道拱部超前管棚+水平旋喷止水预加固+双层衬砌的协同支护方案在工程适应性、工期及造价方面最优。24管隧道采用①—③—②—④顺序开挖,①、③、④号隧道采用CRD法,②号隧道采用三台阶法对隧道沉降及管廊沉降控制最优。3)①号隧道开挖时隧道及管廊沉降变形速率最大。4)地表、管线、管廊及拱顶沉降变形均在5 mm内。

关键词: 四线隧道, 浅埋暗挖, 下穿施工, 综合管廊, 超前加固, 双层衬砌, 管棚, 旋喷桩

Abstract: Technical issues include support and settlement control induced by the fourtrack large crosssection tunnel closely crossing beneath the large utility tunnel in weak and waterrich strata are always encountered. As a result, case investigation, scheme comparison and selection, numerical simulation analysis, and onsite monitoring methods are used to investigate the construction technologies and processes, advanced reinforcement, and supporting parameters of the GuangzhouFoshan intercity passing beneath the Huakang road utility tunnel. The results reveal the following: (1) Based on the active deformation control technology, the collaborative support scheme of the pipe roof under utility tunnel, advanced pipe roof at the tunnel arch, horizontal jet pregrouting and waterproofing, and doublelayer lining are adopted, which is the optimal in terms of adaptability, construction period, and cost. (2) The fourtube tunnel is excavated in order of numbers 1, 3, 2, and 4. The cross diaphragm method is used for tunnel numbers 1, 3, and 4, whereas the threebench method is used for tunnel number 2 to control the settlement of the tunnel and the utility tunnel. (3) During the excavation of the tunnel number 1, the settlement and deformation rate of the tunnel and utility tunnel is the largest. (4) Onsite monitoring results show that the settlements of surface, pipeline, utility tunnel, and tunnel crown are all within 5 mm.

Key words: fourtrack tunnel, shallowburied excavation, undercrossing construction, utility tunnel, advanced reinforcement, doublelayer lining, pipe roof, jet grouting pile

中图分类号: