隧道建设(中英文) ›› 2015, Vol. 35 ›› Issue (6): 589-594.DOI: 10.3973/j.issn.1672-741X.2015.06.016

• 施工技术 • 上一篇    下一篇

遵义市子尹路南延线长距离双连拱隧道快速施工技术

王猛1, 张艳艳2   

  1. (1. 北车建设工程有限责任公司, 北京 100078; 2. 重庆隧源建筑劳务有限公司, 重庆 400000)
  • 收稿日期:2014-07-20 修回日期:2015-05-15 出版日期:2015-06-20 发布日期:2015-06-25
  • 作者简介:王猛(1979—),男,云南宣威人,2014年毕业于重庆交通大学,建筑与土木工程专业,硕士,工程师,主要从事隧道与地下工程施工及项目管理工作。

Rapid Construction Technologies for Longdistance  Doublearch Tunnels: Case Study on Ziyin Tunnel in Zunyi, China

WANG Meng1, ZHANG Yanyan2   

  1. (1. CNR Construction Engineering Co., Ltd., Beijing 100078, China; 2. Chongqing Suiyuan  Construction Service Company, Chongqing 400000, China)
  • Received:2014-07-20 Revised:2015-05-15 Online:2015-06-20 Published:2015-06-25

摘要:

为解决双连拱隧道独头掘进不能提前施工中隔墙进而导致正洞无法开挖的问题,子尹路南延线隧道工程提出“三导洞+联络通道”的施工方法,这在国内尚属首次提出和应用。介绍该工法的基本原理,详细阐述其在子尹路南延线隧道工程中的实施过程。得到的主要结论如下: 1)通过设置联络通道及组织洞内多次交通转换,使得中隔墙得以提前施工,实现了快速施工; 2)通过确定合理施工步序,采用拱架密排对联络通道处加固、加强监测等措施确保了施工过程的安全。

关键词: 双连拱隧道, 导洞, 联络通道, 快速施工, 交通转换

Abstract:

Due to the environmental constraints, the central wall of Ziyin doublearch tunnel cannot be constructed in advance. Therefore, the innovative construction scheme of “3heading + connection passage” is proposed and implemented for the tunnel. In the paper, the principle of the construction scheme is presented and the implementation of the scheme in the tunneling is described in detail. Conclusions drawn are as follows: 1) Due to the installation of the connection passages and the conversion of the traffic organization, the central wall has been constructed in advance and rapid tunneling has been achieved; 2) Due to the rational construction sequence adopted, the intensified steel arch support for the connection passage and the strengthened monitoring, the construction safety has been guaranteed.

Key words: doublearch tunnel, pilot heading, connecting passage, rapid construction, traffic organization conversion