隧道建设(中英文) ›› 2015, Vol. 35 ›› Issue (S1): 5-10.DOI: 10.3973/j.issn.1672-741X.2015.S1.002

• 施工管理 • 上一篇    下一篇

BT模式下地铁土建工程进度管理经验

赵晓华, 刘杨, 崔根群   

  1. (中铁北方投资发展有限公司, 河北石家庄 050011)
  • 收稿日期:2015-04-20 修回日期:2015-06-05 出版日期:2015-07-20 发布日期:2015-08-17
  • 作者简介:赵晓华(1970— ),男,河北石家庄人,1992年毕业于河北建筑工程学院,工业与民用建筑专业,本科,高级工程师,现从事轨道交通建设管理工作。

Experience in Management of Construction Progress of Civil Works of Metro Project under BT Mode

ZHAO Xiaohua, LIU Yang, CUI Genqun   

  1. (China Railway North Investment and Development Co.,Ltd., Shijiazhuang 050011, Hebei, China)
  • Received:2015-04-20 Revised:2015-06-05 Online:2015-07-20 Published:2015-08-17

摘要:

为加快石家庄地铁1号线的土建工程进度,确保洞通等里程碑工期的实现,通过合理确定里程碑工期目标及工期技术参数,高度重视前期工程工作,主动推动站点按期开工,紧抓关键线路站点管控,狠抓短板单位管理,坚持过程预警、严格节点目标、专项考核和劳动竞赛考核,按照“五保”思路全面推进主体工程建设,按照“洞通为本,三通咬合,压茬推进”的工作思路推进各项工作进展,同时通过优化技术方案、强化安全质量、深入对接设计、确保物资供应保障履约,主动替政府与业主着想,帮政府与业主想办法,形成“双铁”建设管理机制,有效保证了土建工程的施工进度。

关键词: BT模式, 石家庄地铁, 工程进度管理

Abstract:

The following measures are taken to speed up the construction progress of the civil works of Line 1 of Shijiazhuang Metro, which is constructed under BT mode: determining the appropriate target dates of the milestones of the construction and the targets of the construction progress; paying adequate attention to the execution of the preliminary works; promoting the ontime commencement of works of each site; implementing strict control of the sites on the critical path; strengthening the management of the construction companies with their construction schedule lagging behind the targets; performing early warning during the construction; implementing target date examination, special examination and incentive program; ensuring the target dates of station construction, shield boring, tunnel breakthrough, track construction and electrical power supply system installation; optimizing the technological schemes; strengthening the safety and quality control; implementing good cooperation with the designer; ensuring the intime material supply; and helping the government authorities and the Client solve their problems. In the paper, the experience in the construction progress management is presented. 

Key words: BT mode, Shijiazhuang Metro, construction progress management