隧道建设(中英文) ›› 2026, Vol. 46 ›› Issue (9): 2001-2010.DOI: 10.3973/j.issn.2096-4498.2026.09.014

• 规划与设计 • 上一篇    下一篇

基于NSGA-Ⅱ目标优化的穿越活动断裂带隧道地震错断后抢修线路拟合

黎旭1, 朵生君2, 任晨宁2, 汪辉武3, 黄鹏莅4, *, 周鸣亮4   

  1. (1. 中国铁路经济规划研究院有限公司, 北京 100038; 2. 中铁第一勘察设计院集团有限公司, 陕西 西安 710043; 3. 中铁二院工程集团有限责任公司, 四川 成都 610031; 4. 同济大学地下建筑与工程系, 上海 200092)
  • 出版日期:2026-09-20 发布日期:2026-09-20
  • 作者简介:黎旭(1989—),男,四川大竹人,西南交通大学桥梁与隧道工程专业在读博士,高级工程师,研究方向为铁路隧道设计、咨询等。E-mail: lixucq@sina.com。*通信作者: 黄鹏莅, E-mail: pengli_h@tongji.edu.cn。

Line Fitting for Emergency Repair of Tunnels Crossing Active Faults After Seismic Displacement Based on Objective Optimization Using Nondominated Sorting Genetic Algorithm Ⅱ

LI Xu1, DUO Shengjun2, REN Chenning2, WANG Huiwu3, HUANG Pengli4, *, ZHOU Mingliang4   

  1. (1. China Railway Economic and Planning Research Institute, Beijing 100038, China; 2. China Railway First Survey and Design Institute Group Co., Ltd., Xi’an 710043, Shaanxi, China; 3. China Railway Eryuan Engineering Group Co., Ltd., Chengdu 610031, Sichuan, China; 4. Department of Geotechnical Engineering, Tongji University, Shanghai 200092, China)
  • Online:2026-09-20 Published:2026-09-20

摘要: 针对地震错断后穿越活动断裂带隧道的快速抢通与线路重拟合问题,建立典型错动几何模型,以拟合段落总长度与超高时变率为目标,缓和曲线长、圆曲线长、夹直线长与圆曲线半径为决策变量,并加以基于欧拉螺线与圆弧参数方程构建的几何闭合约束,通过迭代使拟合线路末端的横向坐标与方位角满足预设容差,以保证工程可实施性。采用NSGA-Ⅱ算法进行多目标进化求解,利用非支配排序与拥挤度保持机制在目标空间获得分布均匀且收敛良好的Pareto解集,并引入线路偏移面积指标I量化评价各方案的横向扩挖规模与工程量指标;基于所得方案评估超高时变率、拟合长度、抗震设防影响及工程规模代价,筛选出若干代表性方案以匹配不同的安全与成本偏好,并提出基于拟合条件的抗震设防范围与断面扩挖建议。以某铁路隧道为例,选取最大突发位错作为最不利工况开展研究。研究结果表明,基于NSGA-Ⅱ多目标优化的线路拟合方法能够在快速抢通需求、工程量指标与运行舒适度、安全性之间提供可操作的折中方案,可为穿越活动断裂带铁路隧道的应急技术预案储备与震后快速抢修决策提供量化依据。

关键词: 活动断裂带, 铁路隧道, 错断, 线路拟合, 快速抢通, NSGA-Ⅱ算法, 多目标优化

Abstract: In this study, a typical geometric model for fault dislocation is established. The model uses total fitting length and superelevation change rate as dual objectives, and the lengths of transition curves, circular curves, and intermediate straight segments, along with the circular curve radius, as decision variables. The geometric closure constraints, based on Euler spirals and parametric equations for circular arcs, ensure engineering feasibility by iteratively aligning the transverse coordinates and azimuth at the end of the fitted line within preset tolerances. The nondominated sorting genetic algorithm Ⅱ (NSGA-Ⅱ) is used for multiobjective evolutionary computation to obtain a wellconverged Pareto solution set in the objective space, and a line offset area index I is introduced to quantitatively evaluate the scale of lateral overexcavation and the engineering volume of various schemes. Based on the resulting solutions, factors such as the rate of superelevation change, fitting length, seismic fortification impacts, and project costs are evaluated to screen representative schemes and recommend seismic fortification ranges and cross-sectional overexcavation. Using a railway tunnel as a case study, the  maximum sudden displacement is selected as the most unfavorable condition. The results indicate that the line-fitting method based on NSGA-Ⅱ multiobjective optimization provides operable tradeoff solutions among rapid restoration, engineering volume, and safety, offering a quantitative basis for the technical reserve in emergency plans and decision-making for rapid post-earthquake repairs.

Key words: active fault zone, railway tunnel, seismic displacement, line fitting, emergency restoration, nondominated sorting genetic-algorithm Ⅱ, multiobjective optimization