Due to the serious damages of the cutting tools of the shield machine after longdistance boring in sand layers, as well as the hardsoft heterogeneous ground conditions in the portion of the tunnel, it would be of great difficulty for the shield machine to drive through the tunnel portion. On basis of the comprehensive evaluations on the requirements of the construction schedules and the feasibility of various connection alternatives, the alternative of mined tunnel is determined to be adopted. The article presents the construction technology of the connection portion between the shielddriven tunnel and the mined tunnel in detail.
Key words: shielddriven tunnel mined tunnel  , countermeasure
CLC Number:
U455.4
MA Xiao-Ding. Construction Technology of Connnection Portion between Shielddriven Tunnel and Mined Tunnel[J]. Tunnel Construction, 2006, 26(增刊1): 22-24.
/ Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2006/V26/I增刊1/22
Current Situation and Development of Causes of Secondary Lining Crack in Loess Tunnel and Countermeasures
Surrounding Rock of Haidong Water Conveyance Tunnel of Central Yunnan Water Diversion Project: Risks and Countermeasures
for Using Ordinary Prestressed Anchor Cables
Research on Construction Risks and Countermeasures of Piperoof Undercutting Method in Saturated Soft Soil