ISSN 2096-4498
CN 44-1745/U
Tunnel Construction ›› 2012, Vol. 32 ›› Issue (2): 197-200.DOI: 10.3973/j.issn.1672-741X.2012.02.014
• wenzhang • Previous Articles Next Articles
DENG Youshu, YANG Yongxiang
Received:
Revised:
Online:
Published:
Abstract: The excavation crosssection of Hongtudi station of Chongqing Metro is 375.8m2. The station is constructed by a combination of TBM method and drill+blast method. The construction technologies adopted for the Metro station is presented in the paper. The construction practice shows that the construction safety and quality of the Metro station is guaranteed and the interactions between the drill+blast construction and TBM boring is minimized.
Key words: largespan Metro station, TBM method, drill+blast method, monitoring
DENG Youshu, YANG Yongxiang. Construction of Largespan Metro Station by Combination of TBM Method and Drill+Blast Method[J]. Tunnel Construction, 2012, 32(2): 197-200.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/10.3973/j.issn.1672-741X.2012.02.014
http://www.suidaojs.com/EN/Y2012/V32/I2/197