Tunnel Construction ›› 2006, Vol. 26 ›› Issue (增刊1): 37-39.DOI: B

• wenzhang • Previous Articles     Next Articles

Some Issues Related to Application of AVN2440DS Shield Machine

WANG He-Hun,  Hu-Jin-Lin   

  1. The 1st TBM Construction Branch of the 2nd Engineering Co.| Ltd. of China Railway
    Tunnel Group, Yanjiao 101601, Beijing, China
  • Received:2006-03-08 Online:2006-05-25 Published:2009-12-31

Abstract:

On basis of the application of the AVN2440DS slurry shield machine, the article presents the maintenance program and structures of the shield machine, as well as the analysis on the electric circuits of the main drive, the common problems occurring during the boring of the shield machine and their countermeasures and the adoption of the domesticmade spare parts. The article can provide reference for other projects in aspect of increasing the availability of the shield machine so as to increase the advance rate and to reduce the construction cost.

Key words: shield machine;maintenance  principle  structure electricity circuits of main drive of cutter head boring, domesticmade spare parts