Tunnel Construction ›› 2007, Vol. 27 ›› Issue (增刊1): 70-72.DOI: B
• wenzhang • Previous Articles Next Articles
HUANG Zhen-Hua
Received:
Revised:
Online:
Published:
Abstract:
The construction ventilation and gascontrol ventilation solutions for Hongshiyan tunnel is presented in the paper. The gushing of the gases, the selection of the construction ventilation methods, the calculation of the air volume and air pressure and the selection of the ventilation equipment are expounded in detail. The paper can provide reference for similar works in the future.
Key words: tunnel gas  , construction ventilation ventilation execution
CLC Number:
U453.5
HUANG Zhen-Hua. Gascontrol Construction Ventilation for Exit Section of Hongshiyan Tunnel[J]. Tunnel Construction, 2007, 27(增刊1): 70-72.