Abstract:
The shield machine has been applying to many long and largesection tunnels crossing the rivers and seas, which are under construction or under planning. The connecting technology between two shield machines in the tunnel has been used many times in some important constructions abroad, but it has no case reference in China. A preliminary study on the construction method of the mechanicstype connection and civiltype connection and their comparisons and the shield machine design, the measurement technology during connection construction, etc are discussed in this paper. Moreover, some key problems of connecting shield machine are presented, which can be reference of the design and construction of the related constructions.
Key words: shield machine  , tunnel  , connection in the ground
CLC Number:
U455.43
WANG Guo-An. Preliminary Study on Construction Technology of Connecting Shield Machines in the Ground[J]. Tunnel Construction, 2007, 27(增刊): 536-541.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/B
http://www.suidaojs.com/EN/Y2007/V27/I增刊/536