In order to construct safely the largescale underground Liangmahe Station on Metro Line 10 in Beijing, which undercrosses the 2 150 sewer pipe, some special ground reinforcement measures were taken and the necessary followup monitoring was carried out. These measures ensured the construction in good progress and the sewer pipeline in safe, which can provide some good references to the other similar constructions.
Key words: 2 150 sewer pipeline  , largepipe umbrella arch  , smallpipe injection  , radial grouting  , waterproof treatment
CLC Number:
TU823.2
TU472.5
WANG He-Wang. Ground Reinforcement Techniques of LargeScale Underground Excavation under 2 150 Sewer Pipeline[J]. Tunnel Construction, 2007, 27(增刊): 559-562.