ISSN 2096-4498
CN 44-1745/U
Tunnel Construction ›› 2007, Vol. 27 ›› Issue (增刊): 433-436.DOI: A
• wenzhang • Previous Articles Next Articles
DIAO Zhi-Gang, LI Chun-Jian
Received:
Revised:
Online:
Published:
Abstract:
Excavating a largesection tunnel in the upper soft and lower hard stratum needs to adopt appropriate construction program, because traditional excavation methods may not meet the request of safety, cost and working progress. The finite element software ANSYS10.0 and the monitoring data are used to analyze the construction method of the largesection tunnels in the stratum with upper soft and lower hard layers in this paper. Through comparing the results from various construction methods, some parameters are presented which can be used in other constructions in the similar stratum.
Key words: upper soft and lower hard stratum  , CRD  , bench cut and crown drift method largesection tunnel  , numerical simulation
CLC Number:
U455.4
DIAO Zhi-Gang, LI Chun-Jian. Study on Construction Method of Large Section Tunnels in Upper Soft and Lower Hard Layers [J]. Tunnel Construction, 2007, 27(增刊): 433-436.
0 / / Recommend
Add to citation manager EndNote|Ris|BibTeX
URL: http://www.suidaojs.com/EN/A
http://www.suidaojs.com/EN/Y2007/V27/I增刊/433
Noise Propagation Characteristics of Tunnel Construction by Drilling and Blasting Method