Construction Technologies for Connection Galleries Constructed by OpencutMethod: Case Study on Shallowburied Shieldbored Tunnels
Received date: 2012-06-19
Revised date: 2012-10-03
Online published: 2013-02-19
The No. 1 connection gallery of shieldbore section at North North stationBeiyuan station section on Xi’an railway transit line 2 locates on connection section of West Tong Highway, North station of Metro line2 and underground park of North railway station. The construction technologies for connection gallery on North Railway stationBeiyuan station section of Xi’an railway transit line 2 constructed by opencut are presented. The key construction technologies and construction organization are summarized. The paper can provide references for similar projects in the future.
ZHAO Puqi . Construction Technologies for Connection Galleries Constructed by OpencutMethod: Case Study on Shallowburied Shieldbored Tunnels[J]. Tunnel Construction, 2012 , 32(增刊1) : 50 -54 . DOI: 10.3973/j.issn.1672-741X.2012.z1.011
/
| 〈 |
|
〉 |