The construction difficulties of connection galleries and waste water pump room are presented, with the construction of connection galleries of shieldbored tunnel on Yitian stationShixia station section of 3151 bid section of Shenzhen Metro as an example. Jet grouting reinforcement technology is replaced by fullface grouting reinforcement technology. The construction technology and technical key points of fullface grouting reinforcement technology are presented. The successful construction of connection galleries of shieldbored tunnel under bad geological conditions is guaranteed after construction program optimization.

Cite this article

ZHANG Jun . Construction Technologies for Connection Galleries of Shieldbored Tunnels under Bad Geological Conditions[J]. Tunnel Construction, 2012 , 32(增刊1) : 95 -98 . DOI: 10.3973/j.issn. 1672-741X.2012.z1.020

Outlines

/

〈 〉