ISSN 2096-4498
CN 44-1745/U
ISSN 2096-4498
CN 44-1745/U
Analysis on and Countermeasures for Technical Difficulties in Construction of Yellow River Crossing Tunnel on Central Route of SouthtoNorth Water Transfer Project
Received date: 2013-01-05
Revised date: 2013-03-08
Online published: 2013-05-16
In the construction of Yellow River Crossing Tunnel on Central Route of SouthtoNorth Water Transfer Project, there are great technical difficulties related to the superdeep mortar wall, superdeep circularshaped diaphragm wall, superdeep circular vertical shaft, superdeep tunnel eye reinforcement and prestressed thin secondary lining. In the paper, analysis is made on these technical difficulties and countermeasures are proposed. In the end, satisfactory effect has been achieved and the tunnel has been built successfully.
ZHENG Qingjun , ZHONG Shengxing . Analysis on and Countermeasures for Technical Difficulties in Construction of Yellow River Crossing Tunnel on Central Route of SouthtoNorth Water Transfer Project[J]. Tunnel Construction, 2013 , 33(5) : 398 -406 . DOI: 10.3973/j.issn.1672-741X.2013.05.012
/
| 〈 |
|
〉 |