Analysis on Transposition of Line 3 and Line 5 of Suzhou Urban Rail Transit in the Industrial Park
Received date: 2013-07-13
Revised date: 2013-11-20
Online published: 2014-01-21
By reviewing the process of the planning of Suzhou urban rail transit network, qualitative and quantitative analyses are made on the 2020 planning network. After local optimization of line 3 and line 7 and by transposing line 3 and line 5 in the Industrial Park, a new plan of line 3 and line 5 is proposed. The analysis on the project implementation and the comparison of the passenger flow tests indicate that the new plan has better network function. The new line 3 combined with line 8 can act as a loop line.
XI Jun , SUN Yuanguang . Analysis on Transposition of Line 3 and Line 5 of Suzhou Urban Rail Transit in the Industrial Park[J]. Tunnel Construction, 2014 , 34(1) : 48 -52 . DOI: 10.3973/j.issn.1672-741X.2014.01.008
/
| 〈 |
|
〉 |