ISSN 2096-4498

   CN 44-1745/U

二维码

Backfilling Grouting Technology for Shieldbored Tunnel in  Waterrich Bedrock Strata: Case Study on Xiangjiang Tunnel on ChangshaZhuzhouXiangtan Intercity Railway

  • REN Chengguo
Expand
  • (China Railway Tunnel Stock Co., Ltd., Zhengzhou 450003, Henan, China)

Received date: 2015-05-22

  Revised date: 2015-08-05

  Online published: 2015-09-22

Abstract

Backfilling grouting behind the segments is the key technology to ensure the safety and construction quality of the shieldbored tunnel, is the key technology to control the ground settlement, and is closely related to the construction cost. Xiangjiang tunnel on ChangshaZhuzhouXiangtan intercity railway is a large diameter shield bored tunnel crossing waterrich bedrock strata. Due to the big annular space behind the segment rings and the flushing erosion effect of the ground water, the simultaneous grouting carried out cannot achieve the expected result. In the paper, the causes for the problems in the simultaneous grouting are analyzed, and countermeasures including “simultaneous grouting, complementary grouting, secondary consolidation grouting and sealing ring execution” are taken and optimized during the tunneling. In the end, the safety and grouting quality are ensured and the construction cost is effectively reduced. 

Cite this article

REN Chengguo . Backfilling Grouting Technology for Shieldbored Tunnel in  Waterrich Bedrock Strata: Case Study on Xiangjiang Tunnel on ChangshaZhuzhouXiangtan Intercity Railway[J]. Tunnel Construction, 2015 , 35(9) : 935 -938 . DOI: 10.3973/j.issn.1672-741X.2015.09.012

Outlines

/

〈 〉