Construction Technologies for Threebenchsevenstep Excavation Method and Equipment Matching of Soft Rock Tunnel on BaojiLanzhou Passengerdedicated Railway Line

  • DAI Runjun ,
  • LI Dongshun ,
  • ZHANG Chengyong
Expand
  • (The Second Engineering Co., Ltd. of China Railway Tunnel Group, Sanhe 065201, Hebei, China)

Received date: 2015-05-24

  Revised date: 2015-07-02

  Online published: 2015-12-24

Abstract

In this paper, the construction keys and equipment matching of threebenchsevenstep excavation method used in construction of Guchengling Tunnel and Lanshan Tunnel on BaojiLanzhou passengerdedicated railway line are presented. The suggestions for the construction are proposed as well.

Cite this article

DAI Runjun , LI Dongshun , ZHANG Chengyong . Construction Technologies for Threebenchsevenstep Excavation Method and Equipment Matching of Soft Rock Tunnel on BaojiLanzhou Passengerdedicated Railway Line[J]. Tunnel Construction, 2015 , 35(S2) : 76 -85 . DOI: 10.3973/j.issn.1672-741X.2015.S2.014

Outlines

/

〈 〉