Settlement Analysis on and Countermeasures for Shallowcovered  Largespan Loess Tunnel Constructed by Mining Method Crossing Underneath Baggagededicated Gallery of Airport

  • TANG Xinquan
Expand
  • (China Railway First Survey & Design Institute Group Co., Ltd., Xi’an 710043, Shaanxi, China)

Received date: 2015-07-19

  Revised date: 2015-09-24

  Online published: 2016-02-01

Abstract

The settlement, deformation and concrete structure crack, may occur to the gallery due to the high construction risk and irrational construction of the shallowcovered largespan loess tunnel. In this paper, in order to satisfy the requirements of the baggagededicated gallery and to control the settlement, 3D numerical simulation method is used to analyze the settlement caused by new tunnel crossing underneath baggagededicated gallery of the airport. In addition, some effective measures, such as strengthening the monitoring and using effective technologies (including excavation step by step, advance support by means of largediameter pipe roof and grout backfilling behind primary support and secondary lining) have been adopted to minimize the settlement of the baggagededicated gallery. The settlement of the gallery floor is limited to about 3 mm, which guarantees the safety of the baggagededicated gallery.

Cite this article

TANG Xinquan . Settlement Analysis on and Countermeasures for Shallowcovered  Largespan Loess Tunnel Constructed by Mining Method Crossing Underneath Baggagededicated Gallery of Airport[J]. Tunnel Construction, 2016 , 36(1) : 80 -85 . DOI: 10.3973/j.issn.1672-741X.2016.01.012

Outlines

/

〈 〉