Study on Risk Management and Control Technologies for Downtop Excavation of Ancillary Works of Metro Station
Received date: 2015-12-21
Revised date: 2016-03-03
Online published: 2016-03-30
The downtop excavation method, with large construction risk, could be chosen when the construction scheme is short. The design, construction and management have to be controlled so as to guarantee the safe construction and to reduce the construction risk. In this paper, the comparison is made among the construction methods of ancillary works of mined Metro station on Line No.7 of Beijing Metro in terms of advantages and disadvantages; and then the construction technology and management technology of downtop excavation method are systematically studied. Finally, the construction scheme of downtop excavation method and the rules of ground surface settlement are analyzed. The monitoring data show that the safe construction has been guaranteed; the influence of downtop excavation on surrounding environment has been minimized and the ground surface settlement has been brought under effective control.
XU Ling , LUO Furong . Study on Risk Management and Control Technologies for Downtop Excavation of Ancillary Works of Metro Station[J]. Tunnel Construction, 2016 , 36(3) : 320 -325 . DOI: 10.3973/j.issn.1672-741X.2016.03.012
/
| 〈 |
|
〉 |